HI!
Just a brief update to our home building project. We've been in constant plan reviews since ...... hmmmmm, don't even know how long! First the reviews by the Roxborough Foundation Design Review Committee, only to find out at the 11th hour that they wanted us to move the house (still only on the plans) 10 feet West and 3 feet North to accommodate our neighbor to the East. That prompted us to go through a "Building Envelope Adjustment" process with Douglas County (including a re-plat and a re-survey). After around 3 months, we've just been notified that we are permitted to submit plans to the Douglas County Building Department!!! Which means that hopefully within 3 weeks or so, we'll be digging dirt.
Cheers!!